Safeworking diagram - 2013
Displays both the number of tracks and the safeworking system in use for a given year.
| 13.281 km | Altona Junction | |
| 18.533 km | Westona | |
| 21.633 km | Laverton Junction |
Legend
| Staff and Ticket | Automatic & Track Control | Double Line Block | |||
| Large Electric Staff | Centralised Train Control | Track Block | |||
| Miniature Electric Staff | Section Authority Working | Yard Limits | |||
| Composite Electric Staff | Train Order Working | Tablet Working |
Sources
- Electric Railways of Victoria - S.E. Doorman and R.G. Henderson
- Newsrail - September 1988
- Altona - Laverton Rail Link Environmental Effects Statement - July 1983 (revised September 1983) - GHD Transport Consultants for the Ministry of Transport