In February 2016 it was announced that the Kororoit Creek Road level crossing on the Altona line would be removed. In October 2016 it was announced that a rail-over-road design, incorporating partial duplication of the Altona Loop, was preferred.
Contracts were signed in May 2017 with work starting soon after. The double track bridge was constructed during a 43-day rail shutdown from 16 June 2018, with the railway reopening a week earlier than expected.
Following the level crossing removal project, double track on the Altona line now ends at the down end of the new rail bridge.
Photos
Nine of 55 images found displayed. Click them to enlarge.
Southern approach to the new bridgeFebruary 5, 2021 |
Steel sculptural elements along the side of the bridgeNovember 17, 2019 |
|
Access pad at the southern end of the bridgeNovember 17, 2019 |
Northern approach to the new bridgeJanuary 20, 2019 |
Reinforced overhead stanchion at Altona JunctionJanuary 20, 2019 |
Stockpiled second hand concrete sleepers at Altona JunctionJanuary 20, 2019 |
Stockpiled second hand concrete sleepers at Altona JunctionJanuary 20, 2019 |
Northern approach to the new bridgeNovember 27, 2018 |